The company carrying out the cabling works on behalf of NEDL have had to delay the connection date from the 21st August 2006 to 30th August 2006.

On the positive side; the disruption to the electricity supply to the Academy will take place approximately between the hours of 8pm and 10pm at night which should make the disruption minimal.

They will still be excavating their trench from the sub-station into
the public highway and up the side of Engineering this week. Then they will be drawing the cable into the trench allowing Surgo to back-fill early next week.