Phase 1 will involve 7 Engineering rooms to be refurbished and 1 Maths room converted in to an additional Engineering room. All rooms will be re-floored in vinyl, new fixed side benching with cupboards underneath and 4 vice technology benches will be installed. All rooms will be re-decorated and the finishing touches will include new tool cupboards, teachers desk, stools and display boards.
-
Engineering refurbishment
@ Wednesday, Jul. 19, 2006 – 19:47:59
Originally the scope of works in Engineering was:
New vinyl floors to 4 rooms.
Consolidate all electrical circuits. -
Steelwork
@ Saturday, Jun. 24, 2006 – 16:43:54
Rome wasn't built in a day but the steelwork is flying up. Monday 19 June and the steelwork is still on the ground, by the end of the week the Sport Hall has taken shape.
21 June, 2006

The main contractor had planned for 2 weeks to get to this stage so had to send the steelworkers off site whilst the drainage diversion was completed. -
Final Meeting With Preferred Contractors
@ Friday, Apr. 07, 2006 – 15:18:27
The purpose of this meeting was to iron out a few details but also to meet the team proposed by the contractors.
Mainly:
Constuction Director
Senior Contracts Manager
Senior Site Manager
Design Manager
In total they are offering 7 full time staff on site. -
Creating A Firm Foundation
@ Tuesday, Apr. 04, 2006 – 16:10:41
Three weeks in and there is still not a great deal to see but we are on course to completing the piling on time. This short video explains the process and why we selected it.
-
Total Number Of Piles
@ Thursday, Mar. 30, 2006 – 23:16:03
Today was a good day for piling with no rain.
24 piles went in today that makes 52 since 4.30 on Monday.The total number of piles is 485 + 65 Contiguous piles.
Total 550They will need to average 24 piles a day to complete by 28 April 2006
-
Contiguous Piled Wall
@ Thursday, Mar. 30, 2006 – 22:48:21
Piling around the tennis courts started today.

The tennis courts are set approximately 1m above ground level and after years of disturbance due to tree root growth are begining to fall away on one side.The engineers have specified contiguous piling around the perimeter.
This is where adjacent piles are almost touching.