enabling works
-
Creating A Firm Foundation from Academy 1316 days old
Three weeks in and there is still not a great deal to see but we are on course to completing the piling on time. This short video explains the process ...
Tags: -
Total Number Of Piles from Academy 1320 days old
Today was a good day for piling with no rain. 24 piles went in today that makes 52 since 4.30 on Monday. The total number of piles is 485 + 65 Contiguous ...
Tags: -
Contiguous Piled Wall from Academy 1320 days old
Piling around the tennis courts started today. The tennis courts are set approximately 1m above ground level and after years of disturbance due to tree ...
Tags: -
Piling has started from Academy 1321 days old
Following site preparation by Hall Construction and a successful drain diversion, piling started on Monday 27th March. Our decision to go for augered ...
Tags: